jain.com

245 MW infrastructure operating capacity across two sites

Company: TeraWulf

Subject kind
facility capacity
Statement date
2024-08-04
Promised amount
245.0 MW
Current status
stated

The claim, verbatim

As of July 31, 2024, operational infrastructure capacity was 245 MW: 195 MW at Lake Mariner and 50 MW at Nautilus.

Source (primary)

terawulf 8-K exhibit (wulfjuly2024opsreport08-.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-31)Live source ↗

Quote: “TeraWulf's operational infrastructure capacity comprised 195 MW at the Lake Mariner facility and 50 MW at the Nautilus facility”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (wulfjuly2024opsreport08-.htm)

Quote: “TeraWulf's operational infrastructure capacity comprised 195 MW at the Lake Mariner facility and 50 MW at the Nautilus facility”

View cached copy (2026-10-31)Live source ↗