Additional 200 MW HPC capacity in 2H2025

Company: TeraWulf

This claim was marked delayed on October 31, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility timeline
Statement date
2024-08-11
Promised by
2025-12-31
Promised amount
200.0 MW
Current status
delayed

What the later record shows

The date slipped

Only 18 critical IT MW of HPC were energized by year-end 2025, far short of an additional 166/200 MW. As of July 2026, CB-4 and CB-5 were still under construction for 2H26 and Q1'27, so no single revised date covers the full scope.

“As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
“UNDER CONSTRUCTION 737 MW ➢ CB - 4 (168 MW, 2H26) ➢ CB - 5 (168 MW, Q127)”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗

Checked October 31, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

An additional 166 MW critical / 200 MW gross of HPC/AI capacity is expected to be available in the second half of 2025.

Source (primary)

terawulf 8-K exhibit (ex992-wulfq22024investor.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-31)Live source ↗

Quote: “Additional 166 /200 MW (1) capacity expected to be available 2H25”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms terawulf 8-K exhibit (ex992-wulfq22024investor.htm)

Quote: “Additional 166 /200 MW (1) capacity expected to be available 2H25”

View cached copy (2026-10-31)Live source ↗

delays Q2 2026 Earnings Update Presentation

Quote: “UNDER CONSTRUCTION 737 MW ➢ CB - 4 (168 MW, 2H26) ➢ CB - 5 (168 MW, Q127)”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

delays View 10-K PDF

Quote: “As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity”

View cached copy (2026-09-01)Live source ↗Archive.org ↗

Record of changes

October 31, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 31, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.