Additional 200 MW HPC capacity in 2H2025
Company: TeraWulf
What the later record shows
The date slipped
Only 18 critical IT MW of HPC were energized by year-end 2025, far short of an additional 166/200 MW. As of July 2026, CB-4 and CB-5 were still under construction for 2H26 and Q1'27, so no single revised date covers the full scope.
“As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity”
2026-02-27 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
“UNDER CONSTRUCTION 737 MW ➢ CB - 4 (168 MW, 2H26) ➢ CB - 5 (168 MW, Q127)”
2026-08-04 · Q2 2026 Earnings Update Presentation View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked October 31, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
An additional 166 MW critical / 200 MW gross of HPC/AI capacity is expected to be available in the second half of 2025.
Source (primary)
terawulf 8-K exhibit (ex992-wulfq22024investor.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-31)Live source ↗
Quote: “Additional 166 /200 MW (1) capacity expected to be available 2H25”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (ex992-wulfq22024investor.htm)
Quote: “Additional 166 /200 MW (1) capacity expected to be available 2H25”
delays Q2 2026 Earnings Update Presentation
Quote: “UNDER CONSTRUCTION 737 MW ➢ CB - 4 (168 MW, 2H26) ➢ CB - 5 (168 MW, Q127)”
delays View 10-K PDF
Quote: “As of December 31, 2025, the Company had energized 18 critical IT MW of HPC capacity”