jain.com

Data center capacity expansion to 510MW

Company: IREN

Subject kind
facility capacity
Statement date
2024-08-27
Promised by
2024-12-31
Promised amount
510.0 MW
Current status
verified

What the later record shows

Delivered on time · happened December 31, 2024

The December 2024 update reports 510MW of operating data centers at month-end.

“Global portfolio now consists of 510MW of operating data centers”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗

Checked October 30, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

IREN plans to expand its data center capacity to 510MW in 2024.

Source (primary)

iren 8-K exhibit (fy24resultspressreleasev.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-30)Live source ↗

Quote: “Date center expansion to 510MW in 2024”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (fy24resultspressreleasev.htm)

Quote: “Date center expansion to 510MW in 2024”

View cached copy (2026-10-30)Live source ↗

confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)

Quote: “Global portfolio now consists of 510MW of operating data centers”

View cached copy (2026-10-21)Live source ↗

Record of changes

October 30, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 30, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.