jain.com

30 EH/s hashrate target 4Q 2024

Company: IREN

Subject kind
guidance
Statement date
2024-09-04
Promised by
2024-12-31
Promised amount
30.0
Current status
verified

What the later record shows

Delivered on time · happened December 31, 2024

The December 2024 update says installed self-mining capacity reached 31 EH/s during the month, exceeding the 30 EH/s 4Q 2024 target.

“Installed self-mining capacity increased to 31 EH/s during the month following completion of Childress Phase 3”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗

Checked October 29, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

IREN expects to reach 30 EH/s installed hashrate at 15 J/TH efficiency in 4Q 2024.

Source (primary)

iren 8-K exhibit (irenaug2024monthlyupdate.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-29)Live source ↗

Quote: “30 EH/s in 4Q 2024 (15 J/TH efficiency)”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (irenaug2024monthlyupdate.htm)

Quote: “30 EH/s in 4Q 2024 (15 J/TH efficiency)”

View cached copy (2026-10-29)Live source ↗

confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)

Quote: “Installed self-mining capacity increased to 31 EH/s during the month following completion of Childress Phase 3”

View cached copy (2026-10-21)Live source ↗

Record of changes

October 29, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 29, 2026 — verified