510MW data center portfolio by end of 2024

Company: IREN

Subject kind
facility capacity
Statement date
2024-09-15
Promised by
2024-12-31
Promised amount
510.0 MW
Current status
verified

What the later record shows

Delivered on time · happened December 31, 2024

The December 2024 monthly update reports 510MW operating at month-end, up from 460MW at the end of November.

“460MW operating at month-end, up by 28% from 360MW”
2024-12-05 · iren 8-K exhibit (nov2024monthlyupdatevdc.htm) View cached copy (2026-10-24)Live source ↗

Checked October 28, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

IREN expects its data center portfolio to reach 510MW by end of 2024.

Source (primary)

iren 8-K exhibit (irennvidiah200purchasevf.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-28)Live source ↗

Quote: “from IREN’s 510MW data center portfolio by end of 2024”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms iren 8-K exhibit (irennvidiah200purchasevf.htm)

Quote: “from IREN’s 510MW data center portfolio by end of 2024”

View cached copy (2026-10-28)Live source ↗

confirms iren 8-K exhibit (nov2024monthlyupdatevdc.htm)

Quote: “460MW operating at month-end, up by 28% from 360MW”

View cached copy (2026-10-24)Live source ↗

Record of changes

October 28, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 28, 2026 — verified
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.