jain.com

ATL expansion not done by Dec 2021

Company: CleanSpark

Subject kind
facility timeline
Statement date
2023-05-24
Current status
stated

The claim, verbatim

Plaintiff alleges that despite several acquisitions to expedite it, the ATL expansion project was still not completed by December 2021.

Source (primary)

Smith v. Bradford — Entry #23: ORDER (RECAP, court_filing)
View cached copy (2026-10-26)Live source ↗

Quote: “but by December 2021, the project was still not completed”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Smith v. Bradford — Entry #23: ORDER

Quote: “but by December 2021, the project was still not completed”

View cached copy (2026-10-26)Live source ↗