Paris colocation capacity live by end of Nov 2024
Company: Nebius
What the later record shows
Delivered on time · happened November 30, 2024
The Q4 2024 release says the Paris GPU cluster was put into operation in November 2024, which meets the end-of-November target.
“In November 2024, Nebius put into operation a GPU cluster in Paris, France, featuring NVIDIA H200 Tensor Core GPUs.”
2025-02-19 · nebius 8-K exhibit (tm257185d1_ex99-1.htm) View cached copy (2026-10-19)Live source ↗
Checked October 25, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
New colocation capacity in Paris, France, under an agreement signed in July 2024, is to be put into operation by the end of November 2024.
Source (primary)
nebius 8-K exhibit (tm2426436d1_ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗
Quote: “Agreement signed in July 2024, new capacity in Paris, France to be put into operation by the end of November 2024”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms nebius 8-K exhibit (tm2426436d1_ex99-1.htm)
Quote: “Agreement signed in July 2024, new capacity in Paris, France to be put into operation by the end of November 2024”
confirms nebius 8-K exhibit (tm257185d1_ex99-1.htm)
Quote: “In November 2024, Nebius put into operation a GPU cluster in Paris, France, featuring NVIDIA H200 Tensor Core GPUs.”