jain.com

Reveille energization targeted 2027

Company: Cipher Mining

Subject kind
facility timeline
Statement date
2024-10-30
Promised by
2027-12-31
Current status
stated

The claim, verbatim

Cipher targets energization of the Reveille data center site in 2027.

Source (primary)

cipher-mining 8-K exhibit (cifr-20241031xex991.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗

Quote: “with energization targeted for 2027”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms cipher-mining 8-K exhibit (cifr-20241031xex991.htm)

Quote: “with energization targeted for 2027”

View cached copy (2026-10-25)Live source ↗