Barber Lake 300 MW interconnection approvals
Company: Cipher Mining
The claim, verbatim
Cipher's Barber Lake site in West Texas is energized and ready for construction. It has approvals for 300 MW of interconnection and the agreements needed to participate in the ERCOT market.
Source (primary)
cipher-mining 8-K exhibit (ciphermining_businessupd.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗
Quote: “Approvals for 300 MW of interconnection / agreements necessary to participate in the ERCOT market”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms cipher-mining 8-K exhibit (ciphermining_businessupd.htm)
Quote: “Approvals for 300 MW of interconnection / agreements necessary to participate in the ERCOT market”