What the later record shows
Delivered on time · happened December 31, 2024
The December 2024 update states the 31 EH/s year-end target was achieved, with installed capacity reaching 31 EH/s during December.
“31 EH/s year-end target achieved (original target of 20 EH/s), highlight video here”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
“Installed self-mining capacity increased to 31 EH/s during the month following completion of Childress Phase 3”
2025-01-06 · iren 8-K exhibit (irendec2024monthlyupdate.htm) View cached copy (2026-10-21)Live source ↗
Checked October 25, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
IREN has 21 EH/s installed and is on track to reach 31 EH/s of installed hashrate in 4Q 2024.
Source (primary)
iren 8-K exhibit (irenoctober2024monthlyin.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗
Quote: “21 EH/s installed (16 J/TH efficiency); 31 EH/s in 4Q 2024”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms iren 8-K exhibit (irenoctober2024monthlyin.htm)
Quote: “21 EH/s installed (16 J/TH efficiency); 31 EH/s in 4Q 2024”
confirms iren 8-K exhibit (irendec2024monthlyupdate.htm)
Quote: “31 EH/s year-end target achieved (original target of 20 EH/s), highlight video here”