Total hash rate target Q1 2025
Company: TeraWulf
What the later record shows
Partly delivered · happened March 31, 2025
The company reported 12.2 EH/s deployed in Q1 2025 against the 13.1 EH/s target. It then guided to only 12 EH/s for Q2–Q4 2025.
“➢ 12.2 EH/s deployed in Q1 2025 ➢ 372 BTC mined in Q1 2025”
2025-05-08 · terawulf 8-K exhibit (wulfq12025investorpresvf.htm) View cached copy (2026-10-15)Live source ↗
“➢ 50 MW (MB-5) expansion online April 2025 ➢ Targeting 225 MW and 12 EH/s for Q2 – Q42025”
2025-05-08 · Investor Presentation View cached copy (2026-10-06)Live source ↗
Checked October 25, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
TeraWulf projects total mining capacity of 13.1 EH/s in Q1 2025, including MB-5 with new S21 Pro miners.
Source (primary)
terawulf 8-K exhibit (wulfq32024investorpres11.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗
Quote: “Maintains Q125 capacity of 13 EH/s, while upgrading fleet to 18.2 J/TH”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms terawulf 8-K exhibit (wulfq32024investorpres11.htm)
Quote: “Maintains Q125 capacity of 13 EH/s, while upgrading fleet to 18.2 J/TH”