jain.com

Ellendale S21 Pro miner swap

Company: Marathon Digital

Subject kind
facility timeline
Statement date
2024-11-11
Promised by
2024-11-30
Promised amount
33000.0 units
Current status
outcome unconfirmed

What the later record shows

Outcome not yet confirmed

The 10-K shows Ellendale at 180 MW and 10.5 EH/s energized. No passage mentions the S19 XP to S21 Pro swap or when it finished.

Checked October 25, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

At the hosted Ellendale site, MARA is replacing 33,000 S19 XPs with S21 Pros, adding about 2.0 EH/s, and expects to complete the transition by the end of November.

Source (primary)

marathon-digital 8-K exhibit (ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗

Quote: “we are adding approximately 2.0 EH/s of hash rate in Ellendale as we replace 33,000 S19 XPs with S21 Pros. We expect to complete the transition by the end of November.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms marathon-digital 8-K exhibit (ex99-1.htm)

Quote: “we are adding approximately 2.0 EH/s of hash rate in Ellendale as we replace 33,000 S19 XPs with S21 Pros. We expect to complete the transition by the end of November.”

View cached copy (2026-10-25)Live source ↗

Record of changes

October 25, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 25, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.