Ohio sites full energization
Company: Marathon Digital
What the later record shows
Partly delivered
The 2025 10-K shows East Ohio (Hannibal plus Hopedale, 225 MW) at 79 MW operational and Central Ohio (Findlay, 150 MW) at 28 MW operational. That is about 107 MW of roughly 375 MW energized, so full energization was not reached by end of 2025; no new date is given.
“Hannibal, Ohio Grid connection 41 159 200 — Hansford County, Texas (2) Colocated with wind generation — 180 180 — Findlay, Ohio Grid connection 26 124 150 1.2”
2025-03-02 · Marathon Digital 10-K filed 2025-03-03 View cached copy (2026-08-31)Live source ↗
“Owned Sites Central Texas East Ohio North Texas Central Ohio Central Nebraska International (2) Total Owned Sites”
2026-03-02 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
“411 79 78 28 127 57 779 273 216 48 536 1,315 550 225 180 150 142 77 1,324”
2026-03-02 · View 10-K PDF View cached copy (2026-09-01)Live source ↗Archive.org ↗
Checked October 25, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
MARA intends to fully energize the three Ohio facilities, with a combined 372 MW of interconnect-approved capacity, by the end of 2025.
Source (primary)
marathon-digital 8-K exhibit (ex99-1.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-10-25)Live source ↗
Quote: “These three facilities have a combined interconnect-approved capacity of 372 megawatts, which we intend to fully energize by the end of 2025.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms marathon-digital 8-K exhibit (ex99-1.htm)
Quote: “These three facilities have a combined interconnect-approved capacity of 372 megawatts, which we intend to fully energize by the end of 2025.”