jain.com

Polaris Forge 3 initial operations

Company: Applied Digital

Subject kind
facility timeline
Statement date
2026-10-03
Promised by
2027-12-31
Promised amount
300.0 MW
Current status
stated

The claim, verbatim

Initial operations at Polaris Forge 3 (300 MW) are expected to commence during calendar year 2027.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-10-03)Live source ↗

Quote: “with initial operations expected to commence during calendar year 2027”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Earnings Release

Quote: “with initial operations expected to commence during calendar year 2027”

View cached copy (2026-10-03)Live source ↗