Additional 300 MW at Ellendale via two buildings; 400 MW total
Company: Applied Digital
The claim, verbatim
Company plans to bring an additional 300 MW online at Ellendale through two additional buildings in the design stage, increasing total HPC capacity to 400 MW.
Source (primary)
Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-10-03)Live source ↗Archive.org ↗
Quote: “we plan to bring an extra 300 MW online through two additional buildings currently in the design stage. This will ultimately increase Ellendale's total HPC capacity to 400 MW.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Earnings Release
Quote: “we plan to bring an extra 300 MW online through two additional buildings currently in the design stage. This will ultimately increase Ellendale's total HPC capacity to 400 MW.”