Jamestown 5MW HPC facility full capacity

Company: Applied Digital

Subject kind
facility capacity
Statement date
2026-10-03
Promised by
2023-12-31
Promised amount
5.0 MW
Current status
stated

The claim, verbatim

The 5MW HPC facility will be completed in two additional stages, with full capacity online by year end 2023.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-10-03)Live source ↗Archive.org ↗

Quote: “The facility will be completed in two additional stages with full capacity online by year end.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Earnings Release

Quote: “The facility will be completed in two additional stages with full capacity online by year end.”

View cached copy (2026-10-03)Live source ↗Archive.org ↗