Ellendale, ND energization by end of February 2023

Company: Applied Digital

Subject kind
facility timeline
Statement date
2026-10-03
Promised by
2023-02-28
Current status
stated

The claim, verbatim

Ellendale facility buildings are under construction, with energization expected before the end of February 2023 (end of fiscal Q3).

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-10-03)Live source ↗Archive.org ↗

Quote: “the Company is actively constructing buildings with energization expected before the end of February.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Earnings Release

Quote: “the Company is actively constructing buildings with energization expected before the end of February.”

View cached copy (2026-10-03)Live source ↗Archive.org ↗