Polaris Forge 2 initial and full capacity

Company: Applied Digital

Subject kind
facility timeline
Statement date
2026-09-29
Promised by
2027-03-31
Promised amount
200.0 MW
Current status
stated

The claim, verbatim

Polaris Forge 2, a $3 billion, 200 MW campus near Harwood, ND (groundbreaking Aug 18, 2025), expects initial capacity in calendar 2026 and full capacity by early calendar 2027.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗

Quote: “Initial capacity is anticipated in calendar 2026, with full capacity online by early calendar 2027.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Earnings Release

Quote: “Initial capacity is anticipated in calendar 2026, with full capacity online by early calendar 2027.”

View cached copy (2026-09-29)Live source ↗Archive.org ↗