Data center hosting capacity 286 MW

Company: Applied Digital

Subject kind
facility capacity
Statement date
2026-09-29
Promised amount
286.0 MW
Current status
stated

The claim, verbatim

The Company currently operates 286 MW of data center hosting capacity: 106 MW in Jamestown and 180 MW in Ellendale, North Dakota.

Source (primary)

Earnings Release (IR page (ir.applieddigital.com), earnings_call)
View cached copy (2026-09-29)Live source ↗Archive.org ↗

Quote: “The Company currently operates 286 MW of data center hosting capacity. Our 106 MW facility in Jamestown, North Dakota, operated at full capacity throughout the year. However, our 180 MW facility in Ellendale”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Earnings Release

Quote: “The Company currently operates 286 MW of data center hosting capacity. Our 106 MW facility in Jamestown, North Dakota, operated at full capacity throughout the year. However, our 180 MW facility in Ellendale”

View cached copy (2026-09-29)Live source ↗Archive.org ↗