jain.com

Completion guarantee for Sandersville Facility

Company: CleanSpark - Project: Sandersville

Subject kind
financing
Statement date
2026-09-17
Current status
stated

The claim, verbatim

CleanSpark will provide a completion guarantee to fund any shortfall needed to complete the Sandersville Facility if the note proceeds are insufficient

Source (primary)

Meta signs 20-year AI data center lease with CleanSpark (NASDAQ: CLSK) as it lines up new debt financing - Stock Titan (-, news_article)
View cached copy (2026-09-20)Live source ↗

Quote: “CleanSpark will provide a completion guarantee to fund any shortfall needed to finish the facility”

How we checked this

Checked on September 25, 2026. The cited source supports every part of this claim.

The press release states that CleanSpark will fund the Issuer as necessary to ensure timely completion of the Sandersville Facility if the note proceeds are insufficient.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://www.stocktitan.net/sec-filings/CLSK/8-k-cleanspark-inc-reports-material-event-4948cb8b11c1.html) in full (38,309 characters, retrieved September 20, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Meta signs 20-year AI data center lease with CleanSpark (NASDAQ: CLSK) as it lines up new debt financing - Stock Titan

Quote: “CleanSpark will provide a completion guarantee to fund any shortfall needed to finish the facility”

View cached copy (2026-09-20)Live source ↗