CleanSpark completion guarantee for Sandersville facility

Company: CleanSpark - Project: Sandersville

Subject kind
facility timeline
Statement date
2026-09-17
Current status
stated

The claim, verbatim

If proceeds from the offering are insufficient, CleanSpark will guarantee completion of the Sandersville Facility

Source (primary)

CleanSpark (CLSK) Stock Jumps as Company Plans Over $2B Offering for Data Center Buildout - CoinGape (-, news_article)
View cached copy (2026-09-20)Live source ↗

Quote: “If proceeds of the offering are not sufficient to complete the facility, CleanSpark will guarantee completion.”

How we checked this

Checked on September 25, 2026. The cited source supports every part of this claim.

The article states that if the offering's proceeds are not enough to complete the facility, CleanSpark will guarantee completion.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://coingape.com/cleanspark-clsk-stock-jumps-as-company-plans-over-2b-offering-for-data-center-buildout/) in full (12,602 characters, retrieved September 20, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark (CLSK) Stock Jumps as Company Plans Over $2B Offering for Data Center Buildout - CoinGape

Quote: “If proceeds of the offering are not sufficient to complete the facility, CleanSpark will guarantee completion.”