Microsoft AI Infrastructure Final Delivery
Company: IREN
The claim, verbatim
IREN will deliver remaining 150 megawatts of computing infrastructure under Microsoft agreement by end of 2026
Source (primary)
JPMorgan Doubles Down on IREN Stock, Raises Price Target to $65 - CoinCodex (-, news_article)
View cached copy (2026-09-14)Live source ↗
Quote: “the remaining 150 megawatts are expected to be delivered by the end of 2026”
How we checked this
Checked on September 23, 2026. The cited source supports every part of this claim.
The article says IREN delivered the first of four 50-megawatt buildings under its Microsoft agreement, and the remaining 150 megawatts are expected by the end of 2026.
Confirmed in the source:
- The delivery is under IREN's Microsoft agreement
- The remaining 150 megawatts are expected to be delivered by the end of 2026
What we did: Read our cached copy of the publisher (https://coincodex.com/article/91939/jpmorgan-doubles-down-on-iren-stock-raises-price-target-to-65/) in full (9,313 characters, retrieved September 14, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms JPMorgan Doubles Down on IREN Stock, Raises Price Target to $65 - CoinCodex
Quote: “the remaining 150 megawatts are expected to be delivered by the end of 2026”