Not a promise: a reported event · happened January 22, 2019
The claim reports an agreement that had already been signed. The 10-K dates the signing of the Contract Manufacturing Agreement to January 22, 2019.
“on January 22, 2019, CleanSpark and Pioneer Power entered into a Contract Manufacturing Agreement, whereby Pioneer Power shall exclusively manufacture parallel switchgears”
2019-12-15 · CleanSpark 10-K filed 2019-12-16 View cached copy (2026-09-13)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Company and Pioneer Power signed an 18-month exclusive contract manufacturing agreement whereby Pioneer Power manufactures parallel switchgears, automatic transfer switches, and related equipment
Source (primary)
CleanSpark 10-Q filed 2019-08-14 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “We also signed a Contract Manufacturing Agreement, whereby Pioneer Power shall exclusively manufacture parallel switchgears, automatic transfer switches and related control and circuit protective equipment for us, for a period of eighteen months.”
How we checked this
Checked on October 11, 2026. The cited source supports part of this claim, but not all of it.
The filing confirms the 18-month agreement and the products covered. The exclusivity runs one way only: Pioneer Power manufactures these products exclusively for CleanSpark, but CleanSpark is free to use other manufacturers.
Confirmed in the source:
- CleanSpark and Pioneer Power signed a Contract Manufacturing Agreement on January 22, 2019 for a period of eighteen months
- Under the agreement, Pioneer Power will exclusively manufacture parallel switchgears, automatic transfer switches and related control and circuit protective equipment for CleanSpark
We could not confirm this from the cited source:
- That the agreement is exclusive for CleanSpark: the filing says it did not create exclusivity for Pioneer and that CleanSpark may use other contract manufacturers
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/827876/000166357719000336/cleanspark10q.htm) in full (126,824 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms CleanSpark 10-Q filed 2019-08-14
Quote: “We also signed a Contract Manufacturing Agreement, whereby Pioneer Power shall exclusively manufacture parallel switchgears, automatic transfer switches and related control and circuit protective equipment for us, for a period of eighteen months.”