Bitcoin mining facility hosting with specified electricity costs
Company: Marathon Digital
The claim, verbatim
The miners will be placed into service in a co-location hosting facility with combined electricity and hosting costs of $0.055 per KwH
Source (primary)
Marathon Digital 8-K filed 2019-08-29 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “The Miners will be placed into service in a Co-Location hosting facility with electricity costs of $0.035 per KwH and $0.02 per KwH for the all-in hosting management. The combined cost of $0.055 per KwH”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Marathon Digital 8-K filed 2019-08-29
Quote: “The Miners will be placed into service in a Co-Location hosting facility with electricity costs of $0.035 per KwH and $0.02 per KwH for the all-in hosting management. The combined cost of $0.055 per KwH”