Bitcoin mining facility hosting with specified electricity costs
Company: Marathon Digital
The claim, verbatim
The miners will be placed into service in a co-location hosting facility with combined electricity and hosting costs of $0.055 per KwH
Source (primary)
Marathon Digital 8-K filed 2019-08-29 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “The Miners will be placed into service in a Co-Location hosting facility with electricity costs of $0.035 per KwH and $0.02 per KwH for the all-in hosting management. The combined cost of $0.055 per KwH”
How we checked this
Checked on September 23, 2026. The cited source supports every part of this claim.
The filing gives the co-location placement, both cost components, and the combined $0.055 per KwH figure.
Confirmed in the source:
- The miners will be placed into service in a co-location hosting facility
- Electricity costs are $0.035 per KwH and hosting management is $0.02 per KwH
- The combined cost is $0.055 per KwH
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1507605/000149315219013483/form8-k.htm) in full (5,311 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Marathon Digital 8-K filed 2019-08-29
Quote: “The Miners will be placed into service in a Co-Location hosting facility with electricity costs of $0.035 per KwH and $0.02 per KwH for the all-in hosting management. The combined cost of $0.055 per KwH”