Scheduled delivery of 10,500 Antminer units through June 2021
Company: Marathon Digital
What the later record shows
Delivered on time · happened June 30, 2021
The 2021 10-K restates the same tranche schedule, saying Bitmain 'delivered' according to it. It also confirms all 10,500 units were received.
“Subject to the timely payment of the purchase price, Bitmain delivered products according to the following schedule: 1,500 units on or before January 31, 2021”
2022-03-09 · Marathon Digital 10-K filed 2022-03-10 View cached copy (2026-09-13)Live source ↗
“As of December 31, 2021, the Company has paid the entire purchase price under this agreement and has received 10,500 units from Bitmain.”
2022-03-09 · Marathon Digital 10-K filed 2022-03-10 View cached copy (2026-09-13)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Scheduled delivery of 1,500 units by January 31, 2021 and 1,800 units each by February 28, 2021 through June 30, 2021
Source (primary)
Marathon Digital 8-K filed 2020-08-18 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “Subject to the timely payment of the purchase price, Bitmain shall deliver products according to the following schedule: 1,500 Units on or before January 31, 2021; and 1,800 units on or before each of February 28, 2021; March 31, 2021; April 30, 2021, May 31, 2021 and June 30, 2021”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
Marathon's August 2020 8-K sets out this exact delivery schedule for the 10,500 Bitmain miners: 1,500 units by January 31, 2021, then 1,800 units each month through June 30, 2021. The filing says these deliveries depend on timely payment of the purchase price.
Confirmed in the source:
- The purchase agreement provided for delivery of 10,500 Antminer S-19 Pro units from Bitmain
- 1,500 units were scheduled for delivery on or before January 31, 2021
- 1,800 units were scheduled for delivery on or before each of February 28, March 31, April 30, May 31 and June 30, 2021
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1507605/000149315220016214/form8-k.htm) in full (6,885 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Marathon Digital 8-K filed 2020-08-18
Quote: “Subject to the timely payment of the purchase price, Bitmain shall deliver products according to the following schedule: 1,500 Units on or before January 31, 2021; and 1,800 units on or before each of February 28, 2021; March 31, 2021; April 30, 2021, May 31, 2021 and June 30, 2021”
confirms Marathon Digital 10-K filed 2022-03-10
Quote: “Subject to the timely payment of the purchase price, Bitmain delivered products according to the following schedule: 1,500 units on or before January 31, 2021”