jain.com

Microgrid deployment at ATL Data Center

Company: CleanSpark - Project: College Park

Subject kind
facility timeline
Statement date
2021-05-05
Current status
stated

The claim, verbatim

Implementation strategy will involve design and installation of multiple microgrids at the ATL Data Center facility to deploy energy technologies and optimize power capacity

Source (primary)

CleanSpark 10-Q filed 2021-05-06 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “implementing this strategy will involve the design and installation of multiple microgrids at the ATL Data Center facility”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms CleanSpark 10-Q filed 2021-05-06

Quote: “implementing this strategy will involve the design and installation of multiple microgrids at the ATL Data Center facility”

View cached copy (2026-09-13)Live source ↗