Bitmain S-19 Pro miners purchase (Oct 2020 contract)

Company: Marathon Digital

This claim was marked delayed on September 15, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
product
Statement date
2021-05-11
Promised by
2021-03-31
Promised amount
21581594.0 USD
Current status
delayed

The claim, verbatim

Company executed contract to purchase additional 10,000 next generation Antminer S-19 Pro ASIC Miners for $21,581,594 with delivery schedule: 2,500 units January 2021, 4,500 units February 2021, 3,000 units March 2021

Source (primary)

Marathon Digital 10-Q/A filed 2021-05-12 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “On October 23, 2020, the Company executed a contract with Bitmain to purchase an additional 10,000 next generation Antminer S-19 Pro ASIC Miners. The 2021 delivery schedule will be 2,500 Units in January, 4,500 Units in February and the final 3,000 Units in March 2021... Bitmain applied a discount of 8.63% to the purchase price adjusting the amount due to $21,581,594.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Marathon Digital 10-Q/A filed 2021-05-12

Quote: “On October 23, 2020, the Company executed a contract with Bitmain to purchase an additional 10,000 next generation Antminer S-19 Pro ASIC Miners. The 2021 delivery schedule will be 2,500 Units in January, 4,500 Units in February and the final 3,000 Units in March 2021... Bitmain applied a discount of 8.63% to the purchase price adjusting the amount due to $21,581,594.”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.