Bitcoin miner hosting capacity

Company: Marathon Digital

This claim was marked delayed on October 10, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility capacity
Statement date
2021-05-26
Promised by
2022-03-31
Promised amount
73000.0 miners
Current status
delayed

What the later record shows

The date slipped

By November 2022, well after the March 2022 target, further deployments at Compute North were delayed by its bankruptcy. Compute North later sold its assets, and Marathon filed claims for breach of the letter of intent. No passage says the full 73,000 miners were hosted.

“The Company’s understanding is that plans for additional deployments have been delayed due to uncertainties associated with the Compute North Bankruptcy.”
2022-11-13 · Marathon Digital 10-Q filed 2022-11-14 View cached copy (2026-09-13)Live source ↗
“Compute North sold substantially all of their assets in a series of 363 sale transactions”
2023-05-09 · Marathon Digital 10-Q filed 2023-05-10 View cached copy (2026-09-13)Live source ↗
“(iii) claims arising from the breach of a letter of intent between us and Compute North LLC”
2025-03-02 · Marathon Digital 10-K filed 2025-03-03 View cached copy (2026-08-31)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Capacity commitment to host 73,000 Bitcoin Miners

Source (primary)

Marathon Digital 8-K filed 2021-05-27 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “host 73,000 Bitcoin Miners”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The filing states that the binding letter of intent with Compute North is to host 73,000 Bitcoin miners.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1507605/000149315221013071/form8-k.htm) in full (4,973 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Marathon Digital 8-K filed 2021-05-27

Quote: “host 73,000 Bitcoin Miners”

View cached copy (2026-09-13)Live source ↗

delays Marathon Digital 10-K filed 2025-03-03

Quote: “(iii) claims arising from the breach of a letter of intent between us and Compute North LLC”

View cached copy (2026-08-31)Live source ↗

delays Marathon Digital 10-Q filed 2023-05-10

Quote: “Compute North sold substantially all of their assets in a series of 363 sale transactions”

View cached copy (2026-09-13)Live source ↗

delays Marathon Digital 10-Q filed 2022-11-14

Quote: “The Company’s understanding is that plans for additional deployments have been delayed due to uncertainties associated with the Compute North Bankruptcy.”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.