73,000 S19 miners hosting with Compute North
Company: Marathon Digital
What the later record shows
Outcome not yet confirmed
Later filings show Marathon had miners at Compute North facilities before Compute North's chapter 11 filing. None say whether all 73,000 S19 miners were deployed, or when.
“Compute North is currently seeking to sell substantially all of its assets, including its direct and indirect ownership interests in the facilities that house the Company’s miners.”
2022-11-13 · Marathon Digital 10-Q filed 2022-11-14 View cached copy (2026-09-13)Live source ↗
“We delivered miners to Compute North, which then installed the mining rigs at those facilities, operated and maintained the mining rigs”
2023-05-09 · Marathon Digital 10-Q filed 2023-05-10 View cached copy (2026-09-13)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Company entered into amended five year hosting agreement with Compute North to host 73,000 S19 miners to be deployed during first two quarters of 2022 at $0.044 per kilowatt hour
Source (primary)
Marathon Digital 8-K filed 2021-12-06 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “entered into an amended five year hosting agreement with Compute North, LLC ("Compute North") to host 73,000 S19 miners to be deployed during the first two quarters of 2022 at a hosting fee of $0.044 per kilowatt hour”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The 8-K's Item 1.01 states that Marathon entered into an amended five-year hosting agreement with Compute North to host 73,000 S19 miners, deployed in the first two quarters of 2022, at $0.044 per kilowatt hour, matching every element of the claim.
Confirmed in the source:
- Marathon Digital Holdings entered into an amended hosting agreement with Compute North, LLC, effective November 30, 2021
- The amended hosting agreement has a five-year term
- The agreement covers hosting of 73,000 S19 miners
- The miners are to be deployed during the first two quarters of 2022
- The hosting fee is $0.044 per kilowatt hour
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1507605/000149315221030586/form8-k.htm) in full (5,420 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Marathon Digital 8-K filed 2021-12-06
Quote: “entered into an amended five year hosting agreement with Compute North, LLC ("Compute North") to host 73,000 S19 miners to be deployed during the first two quarters of 2022 at a hosting fee of $0.044 per kilowatt hour”