Compute North Hosting Capacity

Company: Marathon Digital

This claim was marked delayed on October 10, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility capacity
Statement date
2022-03-09
Promised by
2022-03-31
Promised amount
73000.0 miners
Current status
delayed

What the later record shows

The date slipped · new target June 30, 2022

The amended agreement of November 30, 2021 moved deployment of the 73,000 miners to the first two quarters of 2022. Compute North later went bankrupt and further deployments were delayed.

“entered into an amended five year hosting agreement with Compute North, LLC (“Compute North”) to host 73,000 S19 miners to be deployed during the first two quarters of 2022”
2022-03-09 · Marathon Digital 10-K filed 2022-03-10 View cached copy (2026-09-13)Live source ↗
“The Company’s understanding is that plans for additional deployments have been delayed due to uncertainties associated with the Compute North Bankruptcy.”
2022-11-13 · Marathon Digital 10-Q filed 2022-11-14 View cached copy (2026-09-13)Live source ↗

Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.

The claim, verbatim

Company committed to hosting 73,000 Bitcoin miners at Compute North facility

Source (primary)

Marathon Digital 10-K filed 2022-03-10 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “to host 73,000 Bitcoin Miners over a staged in implementation between October 2021 and March 2022”

How we checked this

Checked on October 11, 2026. The cited source supports every part of this claim.

The 10-K states Marathon entered into a binding letter of intent for Compute North to host 73,000 Bitcoin miners.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1507605/000149315222006446/form10-k.htm) in full (385,382 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms Marathon Digital 10-K filed 2022-03-10

Quote: “to host 73,000 Bitcoin Miners over a staged in implementation between October 2021 and March 2022”

View cached copy (2026-09-13)Live source ↗

delays Marathon Digital 10-Q filed 2022-11-14

Quote: “The Company’s understanding is that plans for additional deployments have been delayed due to uncertainties associated with the Compute North Bankruptcy.”

View cached copy (2026-09-13)Live source ↗

delays Marathon Digital 10-K filed 2022-03-10

Quote: “entered into an amended five year hosting agreement with Compute North, LLC (“Compute North”) to host 73,000 S19 miners to be deployed during the first two quarters of 2022”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 9, 2026 — outcome unconfirmed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
October 10, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.