jain.com

30,000 Antminer S-19j Pro purchase with delivery through June 2022

Company: Marathon Digital

This claim was marked delayed on September 15, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
acquisition
Statement date
2022-03-09
Promised by
2022-06-30
Promised amount
126000000.0 USD
Current status
delayed

The claim, verbatim

Executed contract with Bitmain to purchase 30,000 S-19j Pro ASIC Miners with delivery schedule January through June 2022 for $126 million

Source (primary)

Marathon Digital 10-K filed 2022-03-10 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “On July 30, 2021, Marathon Digital Holdings, Inc. (the "Company") entered into a fully executed contract with Bitmain to purchase an additional 30,000 S-19j Pro ASIC Miners, with 5,000 units scheduled to be delivered in each of January 2022, February 2022, March 2022, April 2022, May 2022, and June 2022. The purchase price is $126,000,000”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Marathon Digital 10-K filed 2022-03-10

Quote: “On July 30, 2021, Marathon Digital Holdings, Inc. (the "Company") entered into a fully executed contract with Bitmain to purchase an additional 30,000 S-19j Pro ASIC Miners, with 5,000 units scheduled to be delivered in each of January 2022, February 2022, March 2022, April 2022, May 2022, and June 2022. The purchase price is $126,000,000”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.