Miner Equipment Delivery Commitment
Company: TeraWulf
What the later record shows
The date slipped · new target March 31, 2023
By December 2022 the same disclosure cited only 44,450 miners, with delivery extending to March 2023, instead of 58,000 by December 2022. Both the scope and the timeline changed.
“Despite securing Equipment Supply Agreements that provide for delivery of an aggregate total of 44,450 miners between January 2022 and March 2023”
2022-12-11 · TeraWulf 424B5 filed 2022-12-12 View cached copy (2026-09-13)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Equipment Supply Agreements provide for delivery of aggregate total of 58,000 miners between January and December 2022
Source (primary)
TeraWulf 424B5 filed 2022-03-17 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “Equipment Supply Agreements that provide for delivery of an aggregate total of 58,000 miners between January 2022 and December 2022”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
TeraWulf's March 2022 prospectus supplement states that its Equipment Supply Agreements provide for delivery of an aggregate total of 58,000 miners between January 2022 and December 2022. The same passage notes that delivery of 20,000 MV7 miners was still under negotiation, but the claim as worded matches the document.
Confirmed in the source:
- TeraWulf's Equipment Supply Agreements provide for delivery of an aggregate total of 58,000 miners
- The scheduled delivery window for those miners runs from January 2022 to December 2022
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1083301/000110465922034743/tm222878-8_424b5.htm) in full (262,726 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms TeraWulf 424B5 filed 2022-03-17
Quote: “Equipment Supply Agreements that provide for delivery of an aggregate total of 58,000 miners between January 2022 and December 2022”
delays TeraWulf 424B5 filed 2022-12-12
Quote: “Despite securing Equipment Supply Agreements that provide for delivery of an aggregate total of 44,450 miners between January 2022 and March 2023”