Bitcoin Miner Procurement

Company: TeraWulf

This claim was marked delayed on September 15, 2026. Recorded automatically from the cited source when it was published, then queued for evidence review.

How this was decided: Automated extraction from the cited source. The claim is preserved below exactly as it was originally published, so the record shows what was asserted as well as what became of it.

Subject kind
facility capacity
Statement date
2022-03-30
Promised by
2022-12-31
Promised amount
78000.0 units
Current status
delayed

The claim, verbatim

Entered into purchase agreements with two bitcoin miner manufacturers to acquire up to 78,000 bitcoin miners with expected delivery between December 2021 and December 2022

Source (primary)

TeraWulf 10-K filed 2022-03-31 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “During 2021, the Company entered into certain purchase agreements with two bitcoin miner manufacturers to acquire up to a total of 78,000 bitcoin miners, which are expected to be delivered between December 2021 and December 2022”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms TeraWulf 10-K filed 2022-03-31

Quote: “During 2021, the Company entered into certain purchase agreements with two bitcoin miner manufacturers to acquire up to a total of 78,000 bitcoin miners, which are expected to be delivered between December 2021 and December 2022”

View cached copy (2026-09-13)Live source ↗

Record of changes

September 14, 2026 — stated
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.
September 15, 2026 — delayed
Automated extraction from the cited source. Recorded automatically from the cited source when it was published, then queued for evidence review.