Significant monthly ramp of operations
Company: TeraWulf
The claim, verbatim
Company expects to significantly ramp operations monthly with completion of data center infrastructure at Lake Mariner and Nautilus Cryptomine facilities
Source (primary)
TeraWulf 8-K filed 2022-07-01 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “expects to significantly ramp operations monthly with the completion of the data center infrastructure at its Lake Mariner and Nautilus Cryptomine facilities”
How we checked this
Checked on September 22, 2026. The cited source supports every part of this claim.
The document states this expectation for both named facilities.
Confirmed in the source:
- Company expects to significantly ramp operations monthly with completion of data center infrastructure at Lake Mariner and Nautilus Cryptomine facilities
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1083301/000110465922076754/tm2220243d1_8k.htm) in full (7,344 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms TeraWulf 8-K filed 2022-07-01
Quote: “expects to significantly ramp operations monthly with the completion of the data center infrastructure at its Lake Mariner and Nautilus Cryptomine facilities”