Jamestown, ND air-cooled expansion
Company: Marathon Digital - Project: Jamestown
What the later record shows
Partly delivered
As of December 31, 2023, Jamestown had 10,000 S19 XPs, fewer than the 10,400 additional air-cooled units planned for Q1 2023. No passage gives a deployment date.
“Jamestown, North Dakota APLD affiliate 40 1.4 10,000 S19 XPs, with another 768 units of immersion”
2024-02-27 · Marathon Digital 10-K filed 2024-02-28 View cached copy (2026-08-31)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
The Company plans to deploy 10,400 air-cooled units at Jamestown, ND in Q1 2023.
Source (primary)
Marathon Digital 10-K filed 2023-03-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “with planned deployments of another 10,400 air-cooled units during the first quarter of 2023”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The 10-K's operations summary for Jamestown, ND states there were planned deployments of another 10,400 air-cooled units during the first quarter of 2023.
Confirmed in the source:
- Marathon planned to deploy another 10,400 air-cooled units at its Jamestown, ND site
- The planned deployment was scheduled for the first quarter of 2023
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1507605/000149315223007879/form10-k.htm) in full (445,884 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Marathon Digital 10-K filed 2023-03-16
Quote: “with planned deployments of another 10,400 air-cooled units during the first quarter of 2023”