Odessa Facility full buildout target
Company: Cipher Mining
The claim, verbatim
When fully built at 207 MW, Odessa will operate 60,000 miners generating 6.2 EH/s
Source (primary)
Cipher Mining 10-K filed 2023-03-14 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “Once built out to the full 207MW of its electrical power capacity, we anticipate the Odessa Site will operate approximately 60,000 miners, capable of generating approximately 6.2 EH/s”
How we checked this
Checked on September 21, 2026. The cited source supports every part of this claim.
The full-buildout figures appear verbatim in the document.
Confirmed in the source:
- Once fully built to 207 MW, Odessa is anticipated to operate approximately 60,000 miners
- Capable of generating approximately 6.2 EH/s
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1819989/000095017023007793/cifr-20221231.htm) in full (564,500 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Cipher Mining 10-K filed 2023-03-14
Quote: “Once built out to the full 207MW of its electrical power capacity, we anticipate the Odessa Site will operate approximately 60,000 miners, capable of generating approximately 6.2 EH/s”
