Ellendale ND site energization

Company: Marathon Digital - Project: Ellendale

Subject kind
facility timeline
Statement date
2023-03-15
Promised amount
57000.0 units
Current status
stated

The claim, verbatim

Approximately 57,000 S19 XP mining rigs expected to be deployed at Ellendale, ND during first half 2023 with energization starting late first quarter 2023

Source (primary)

Marathon Digital 10-K filed 2023-03-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “Approximately 57,000 S19 XPs are expected to be deployed at this site during the first half of 2023. Energization is expected to start late in the first quarter of 2023.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Marathon Digital 10-K filed 2023-03-16

Quote: “Approximately 57,000 S19 XPs are expected to be deployed at this site during the first half of 2023. Energization is expected to start late in the first quarter of 2023.”