Garden City TX immersion expansion
Company: Marathon Digital - Project: Garden City
The claim, verbatim
19 MW of immersion capacity planned for deployment at Garden City, TX during 2023
Source (primary)
Marathon Digital 10-K filed 2023-03-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “Our current expansion plans call for the deployment of 19 MW of immersion from a combination of new capacity and replacement of air-cooled units for immersion during 2023.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Marathon Digital 10-K filed 2023-03-16
Quote: “Our current expansion plans call for the deployment of 19 MW of immersion from a combination of new capacity and replacement of air-cooled units for immersion during 2023.”