Jamestown ND immersion cooling unit deployment
Company: Marathon Digital - Project: Jamestown
What the later record shows
Delivered; the record does not say when
The FY2023 10-K lists 768 immersion units at Jamestown as of year-end 2023. It does not say whether they were deployed by the end of Q2 2023.
“Jamestown, North Dakota APLD affiliate 40 1.4 10,000 S19 XPs, with another 768 units of immersion”
2024-02-27 · Marathon Digital 10-K filed 2024-02-28 View cached copy (2026-08-31)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
768 immersion cooling units planned for deployment at Jamestown, ND facility during second quarter 2023
Source (primary)
Marathon Digital 10-K filed 2023-03-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “the Company plans to deploy 768 units in immersion on the site during the second quarter of 2023”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The filing states Marathon plans to deploy 768 immersion units at Jamestown in Q2 2023.
Confirmed in the source:
- Marathon planned to deploy 768 units in immersion at the Jamestown, ND site
- The deployment was planned for the second quarter of 2023
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1507605/000149315223007879/form10-k.htm) in full (445,884 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Marathon Digital 10-K filed 2023-03-16
Quote: “the Company plans to deploy 768 units in immersion on the site during the second quarter of 2023”
confirms Marathon Digital 10-K filed 2024-02-28
Quote: “Jamestown, North Dakota APLD affiliate 40 1.4 10,000 S19 XPs, with another 768 units of immersion”