Ellendale ND facility energization timing
Company: Marathon Digital - Project: Ellendale
What the later record shows
Delivered; the record does not say when
The FY2023 10-K shows Ellendale with 180 MW energized as of December 31, 2023, so energization did happen. No passage gives the start date, so it is unclear whether it began in late Q1 2023.
“Site Location Mega-watts Energized Exahash Lease Expiration McCamey, Texas 216 7.7 August 2027 Garden City, Texas 100 4.5 July 2027 Ellendale, North Dakota 180 7.8 July 2027”
2024-02-27 · Marathon Digital 10-K filed 2024-02-28 View cached copy (2026-08-31)Live source ↗
Checked October 10, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
Energization of Ellendale, ND facility expected to start late in first quarter 2023
Source (primary)
Marathon Digital 10-K filed 2023-03-16 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “Energization is expected to start late in the first quarter of 2023”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The filing states that energization at Ellendale is expected to start late in Q1 2023.
Confirmed in the source:
- Energization of the Ellendale, ND site is expected to start late in the first quarter of 2023
What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1507605/000149315223007879/form10-k.htm) in full (445,884 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms Marathon Digital 10-K filed 2023-03-16
Quote: “Energization is expected to start late in the first quarter of 2023”
confirms Marathon Digital 10-K filed 2024-02-28
Quote: “Site Location Mega-watts Energized Exahash Lease Expiration McCamey, Texas 216 7.7 August 2027 Garden City, Texas 100 4.5 July 2027 Ellendale, North Dakota 180 7.8 July 2027”