Applied Digital began construction of a 5 MW specialized GPU processing facility designed for graphics processing and high-performance computing applications
Source (primary)
Applied Digital S-3 filed 2023-05-17 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗
Quote: “On December 14, 2022, the Company began construction of its latest specialized processing center, a 5 MW facility next to the Company's currently operating 100-MW hosting facility in Jamestown, North Dakota. This separate and unique building, designed and purpose-built for Graphics Processing Units ("GPUs"), will sit separate from the Company's current buildings and plans to host more traditional high performance computing ("HPC") applications, such as natural language processing, machine learning, and additional HPC developments.”
How we checked this
This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.
Additional evidence
confirms Applied Digital S-3 filed 2023-05-17
Quote: “On December 14, 2022, the Company began construction of its latest specialized processing center, a 5 MW facility next to the Company's currently operating 100-MW hosting facility in Jamestown, North Dakota. This separate and unique building, designed and purpose-built for Graphics Processing Units ("GPUs"), will sit separate from the Company's current buildings and plans to host more traditional high performance computing ("HPC") applications, such as natural language processing, machine learning, and additional HPC developments.”