jain.com

Supreme Court ruling on limited recourse equipment financing arrangements

Company: IREN

Subject kind
financing
Statement date
2023-08-10
Current status
stated

The claim, verbatim

The Supreme Court of British Columbia affirmed that Bitcoin mined by the Company is not collateral for the equipment financing facilities and there is no parent guarantee. The court declared hashpower services transactions void, with an estimated value discrepancy of $3–$11.9 million between value received and consideration paid.

Source (primary)

IREN 6-K filed 2023-08-11 (SEC EDGAR, sec_filing)
View cached copy (2026-09-13)Live source ↗

Quote: “the Court issued its ruling affirming the Company's position that, among other things, the Bitcoin mined by the Company is not collateral securing such facilities and there is no parent guarantee with respect to the equipment financing facilities, and no relief in respect of substantive consolidation was granted. However, the Court declared transactions pursuant to hashpower services provided by the Non-Recourse SPVs to the Company to be void (the Court noted that based on the submissions to date, the discrepancy between the value that the Company received for the hashpower and the consideration paid to the Non-Recourse SPVs is between $3 million and $11.9 million)”

How we checked this

Attempted on September 21, 2026. We could not read enough of the cited source to check this claim.

The verification run did not return a result for this claim (claude -p exit 1: b'').

What we did: Read our cached copy of SEC EDGAR (https://www.sec.gov/Archives/edgar/data/1878848/000114036123039183/brhc20057412_6k.htm) in full (7,287 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms IREN 6-K filed 2023-08-11

Quote: “the Court issued its ruling affirming the Company's position that, among other things, the Bitcoin mined by the Company is not collateral securing such facilities and there is no parent guarantee with respect to the equipment financing facilities, and no relief in respect of substantive consolidation was granted. However, the Court declared transactions pursuant to hashpower services provided by the Non-Recourse SPVs to the Company to be void (the Court noted that based on the submissions to date, the discrepancy between the value that the Company received for the hashpower and the consideration paid to the Non-Recourse SPVs is between $3 million and $11.9 million)”

View cached copy (2026-09-13)Live source ↗