jain.com

Lake Mariner CB4 and CB5 design capacity optimization

Company: TeraWulf

Subject kind
product
Statement date
2026-02-25
Promised amount
168.0 MW
Current status
stated

The claim, verbatim

Design optimization increased critical IT capacity for CB4 and CB5 buildings from 162 MW to 168 MW per building without increasing base construction budgets

Source (primary)

terawulf 8-K exhibit (a_wulfearningsrelease2026-.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-13)Live source ↗

Quote: “Through design optimization across later phases, critical IT capacity for CB4 and CB5 increased from 162 MW to 168 MW per building without increasing base construction budgets”

How we checked this

Checked on September 21, 2026. The cited source supports every part of this claim.

The document states verbatim that design optimization raised CB4 and CB5 capacity from 162 MW to 168 MW per building without increasing base construction budgets.

Confirmed in the source:

What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330126000026/a_wulfearningsrelease2026-.htm) in full (26,590 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms terawulf 8-K exhibit (a_wulfearningsrelease2026-.htm)

Quote: “Through design optimization across later phases, critical IT capacity for CB4 and CB5 increased from 162 MW to 168 MW per building without increasing base construction budgets”

View cached copy (2026-09-13)Live source ↗