Core42 HPC lease contract
Company: TeraWulf
What the later record shows
Partly delivered
Of the 60 MW Core42 contract, 18 critical IT MW had commenced by December 31, 2025. The rest is expected to commence in 2026.
“Certain of the Core42 Leases commenced in 2025 which comprised 18 critical IT MW HPC lease capacity as of December 31, 2025.”
2026-02-26 · TeraWulf 10-K filed 2026-02-27 View cached copy (2026-08-31)Live source ↗
“The remainder of the HPC Leases are expected to commence in 2026.”
2026-02-26 · TeraWulf 10-K filed 2026-02-27 View cached copy (2026-08-31)Live source ↗
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
60 critical IT MW contracted with Core42, commenced in 2025 and commencing in 2026
Source (primary)
terawulf 8-K exhibit (a_wulfearningsrelease2026-.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-13)Live source ↗
Quote: “60 critical IT MW with Core42, commenced in 2025 and commencing in 2026”
How we checked this
Checked on October 11, 2026. The cited source supports every part of this claim.
The earnings release lists 60 critical IT MW with Core42 at Lake Mariner, commenced in 2025 and commencing in 2026.
Confirmed in the source:
- TeraWulf's Lake Mariner campus has a long-term lease commitment with Core42 for 60 critical IT MW
- The Core42 lease commenced in 2025 and continues commencing in 2026
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330126000026/a_wulfearningsrelease2026-.htm) in full (26,590 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (a_wulfearningsrelease2026-.htm)
Quote: “60 critical IT MW with Core42, commenced in 2025 and commencing in 2026”