Annual critical IT capacity target
Company: TeraWulf
The claim, verbatim
TeraWulf is targeting 250-500 MW of new critical IT capacity annually through 2030.
Source (primary)
terawulf 8-K exhibit (terawulfq42025investorpr.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-13)Live source ↗
Quote: “Targeting +250–500 MW of New Critical IT Capacity Annually”
How we checked this
Checked on September 21, 2026. The cited source supports every part of this claim.
The document states 'Targeting +250–500 MW of New Critical IT Capacity Annually' and describes 'Control of sufficient sites to deliver +250–500 MW annually through 2030.'
Confirmed in the source:
- TeraWulf is targeting +250–500 MW of new critical IT capacity annually
- TeraWulf targets this annual capacity addition through 2030
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330126000026/terawulfq42025investorpr.htm) in full (29,065 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (terawulfq42025investorpr.htm)
Quote: “Targeting +250–500 MW of New Critical IT Capacity Annually”