CB-3 lease start
Company: TeraWulf
What the later record shows
Outcome not yet confirmed
No passage reports a CB-3 lease start or lease signing. P40 only describes an earnout payable upon execution of a CB-3 lease.
Checked October 9, 2026 against filings, releases and reporting published after the claim was made. Quotes are verbatim from the linked documents.
The claim, verbatim
CB-3 (42 MW) is expected to have lease start by July 2026.
Source (primary)
terawulf 8-K exhibit (terawulfq42025investorpr.htm) (SEC EDGAR (8-K Ex), press_release)
View cached copy (2026-09-13)Live source ↗
Quote: “CB-3 (42 MW, May)... Estimated Lease Start Date... 7/31/26”
How we checked this
Checked on October 11, 2026. The cited source supports part of this claim, but not all of it.
The document confirms CB-3's 42 MW size and a May 2026 timing. The lease-start table's columns cannot be read reliably, so the document does not establish that the July 2026 date applies to CB-3.
Confirmed in the source:
- CB-3 is a 42 MW building
- CB-3 is scheduled for May 2026 in the presentation's 2026 construction timeline
We could not confirm this from the cited source:
- The source does not clearly tie a July 31, 2026 lease start date to CB-3; in the garbled lease-start table, that date more plausibly belongs to another building or to a prior estimate
That does not mean it is false — only that this source does not establish it, as of the date above. If we find a source that settles it, we will re-check and update this page.
What we did: Read our cached copy of SEC EDGAR (8-K Ex) (https://www.sec.gov/Archives/edgar/data/1083301/000108330126000026/terawulfq42025investorpr.htm) in full (29,065 characters, retrieved September 13, 2026) and checked each assertion in the claim against it.
Additional evidence
confirms terawulf 8-K exhibit (terawulfq42025investorpr.htm)
Quote: “CB-3 (42 MW, May)... Estimated Lease Start Date... 7/31/26”