jain.com

Beacon Point Nueces County facility lease

Company: Hut 8 - Project: Beacon Point

Subject kind
facility timeline
Statement date
2026-09-07
Current status
stated

The claim, verbatim

15-year data center facility lease in Nueces County, Texas to be leased by Nvidia

Source (primary)

Why Hut 8 (HUT) Is Up 19.0% After Pivoting Bitcoin Mining Power Into AI Data Centers - simplywall.st (-, news_article)
View cached copy (2026-09-10)Live source ↗

Quote: “The Beacon Point expansion in Nueces County, Texas, is the clearest example of this shift, with a 15 year, US$9.8 billion base-term lease tied to Nvidia and Anthropic”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Why Hut 8 (HUT) Is Up 19.0% After Pivoting Bitcoin Mining Power Into AI Data Centers - simplywall.st

Quote: “The Beacon Point expansion in Nueces County, Texas, is the clearest example of this shift, with a 15 year, US$9.8 billion base-term lease tied to Nvidia and Anthropic”

View cached copy (2026-09-10)Live source ↗