Texas ERCOT conditional capacity classifications

Company: CleanSpark

Subject kind
facility capacity
Statement date
2026-09-09
Promised amount
585.0 MW
Current status
stated

The claim, verbatim

Received ERCOT conditional batch-zero classifications for 585 MW of contracted baseload capacity and 300 MW of studied load capacity in Texas

Source (primary)

CleanSpark Mines More Bitcoin But Sells Even More in August - Blockonomi (-, news_article)
View cached copy (2026-09-09)Live source ↗Archive.org ↗

Quote: “In Texas, ERCOT issued conditional batch-zero classifications covering 585 MW of contracted baseload capacity and 300 MW of studied load capacity”

How we checked this

Checked on September 20, 2026. The cited source supports every part of this claim.

The document states ERCOT issued conditional batch-zero classifications covering both 585 MW of contracted baseload and 300 MW of studied load capacity.

Confirmed in the source:

What we did: Read our cached copy of the publisher (https://blockonomi.com/cleanspark-mines-more-bitcoin-but-sells-even-more-in-august/) in full (6,115 characters, retrieved September 9, 2026) and checked each assertion in the claim against it.

Additional evidence

confirms CleanSpark Mines More Bitcoin But Sells Even More in August - Blockonomi

Quote: “In Texas, ERCOT issued conditional batch-zero classifications covering 585 MW of contracted baseload capacity and 300 MW of studied load capacity”

View cached copy (2026-09-09)Live source ↗Archive.org ↗