jain.com

949 MW contracted IT capacity

Company: Hut 8

Subject kind
facility capacity
Statement date
2026-08-04
Promised amount
949.0 MW
Current status
stated

The claim, verbatim

Hut 8 reported 949 MW of contracted IT capacity across River Bend and Beacon Point.

Source (primary)

Hut 8 adds US$1.07B secured credit line for AI campuses - mugglehead.com (-, news_article)
View cached copy (2026-09-29)Live source ↗Archive.org ↗

Quote: “Hut 8 reported 949 megawatts of contracted IT capacity across River Bend and Beacon Point”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms Hut 8 adds US$1.07B secured credit line for AI campuses - mugglehead.com

Quote: “Hut 8 reported 949 megawatts of contracted IT capacity across River Bend and Beacon Point”

View cached copy (2026-09-29)Live source ↗Archive.org ↗