jain.com

Camp Pendleton microgrid work completion

Company: CleanSpark

Subject kind
facility timeline
Statement date
2019-01-14
Promised by
2019-03-31
Current status
stated

The claim, verbatim

CleanSpark expects to complete its scope of work on the Camp Pendleton microgrid installation in early 2019

Source (primary)

CleanSpark 10-K filed 2019-01-15 (SEC EDGAR, sec_filing)
View cached copy (2026-09-27)Live source ↗

Quote: “The Company begin on-site work for this project in February of 2018 and expects to complete its scope of work in early 2019.”

How we checked this

This claim has not yet been checked assertion-by-assertion against its source. It carries a cited source and quote, but the deeper check has not run. When it does, the result appears here whatever it says.

Additional evidence

confirms CleanSpark 10-K filed 2019-01-15

Quote: “The Company begin on-site work for this project in February of 2018 and expects to complete its scope of work in early 2019.”

View cached copy (2026-09-27)Live source ↗